Busiest road gets much-needed refresh

Published on 26 November 2026

Ipswich City Council’s busiest road just got a much-needed refresh.

Augusta Parkway at Brookwater – with more than 30,000 traffic movements every day – has undergone major road pavement reconstruction works.

Division 2 Councillor Paul Tully said the $3.4 million project, which started in September, wrapped up this month.

“Motorists will be delighted that the new surface is completed and will extend the service life of this section of Augusta Parkway by a further 20 years,” Cr Tully said.

“That road has been the busiest council-owned road for a decade, with more than 30,000 cars and trucks travelling over it every day of the year.

“With the Springfield region growing by the day, right through to Ripley and Redbank Plains, and accessing the Centenary Highway, it is such a vital route for all forms of transport and needs to be in the best shape for as long as possible.”

Stage One of the project involved resurfacing between Santa Monica Drive to Tournament Drive/Mount Juillerat Drive Roundabout.

A future Stage Two Stage 2 will see further resurfacing between Woogaroo Creek Bridge and Santa Monica Drive, and Stage 3 a full reconstruction from Tournament Drive/Mount Juillerat Drive Roundabout to Eden Station Drive.

Deputy Mayor and Division 2 Councillor Nicole Jonic said with Augusta Parkway so busy throughout the day, the work extended over seven weeks and was done at night to minimise the disruption to motorists.

“Crews had to remove about 900m of existing road pavement between Santa Monica Drive and the Tournament Drive and Mount Juillerat Drive roundabout, install new road pavement and associated line marking, and undertake minor tree trimming and landscape reinstatement works,” Deputy Mayor Jonic said.

“Council was able to minimise disruption by working at night. I thank motorists and nearby residents and businesses for their patience while these works were completed.”